  "fixture": true,
  "version": "1.0",
  "limitations": "Fictional administrative teaching material. No actual drawings, contracts, carriers, client results, engineering instructions, legal interpretation, carrier verification or movement authorization. Actual acceptance-test results are unrun.",
  "cutoff": "2026-11-04T12:00:00-06:00",
  "project_id": "CONST-401",
  "rfi": {
    "id": "RFI-401",
    "question": "Panel-type references differ between A-201 revision B and FS-04 revision C",
    "source_references": [
      "A-201 rev B",
      "FS-04 rev C"
    ],
    "supplier_comment": {
      "id": "COMMENT-401",
      "proposal": "Use panel type P2",
      "status": "informal_proposal_not_designated_answer"
    },
    "designated_response": {
      "id": "RESP-401",
      "recorded_at": "2026-11-04T10:00:00-06:00",
      "recorded_by": "Authorized role under fictional project process",
      "text": "Coordinate panel selection in the drawing package; await reviewed release",
      "status": "designated_in_example_process"
    },
    "information_state": "response_recorded",
    "scope_limit": "Response record alone does not decide drawing release or commercial authority"
  },
  "drawing": {
    "id": "A-201",
    "earlier_revision": "B",
    "received_revision": "C",
    "transmittal_id": "TX-401",
    "received_at": "2026-11-04T11:00:00-06:00",
    "review_status": "pending",
    "field_release_status": "not_released",
    "next_owner": "Document controller",
    "next_action": "Review source identity and issue purpose; record permitted release status"
  },
  "field_package": {
    "id": "FP-401",
    "drawing_reference": "A-201 rev C",
    "release": "held_pending_decisions",
    "recipients": [
      {
        "id": "TRADE-401A",
        "acknowledged": false
      },
      {
        "id": "TRADE-401B",
        "acknowledged": false
      }
    ],
    "acknowledged_count": 0,
    "expected_recipient_count": 2,
    "actual_recipient_addresses": null,
    "next_owner": "Field release owner",
    "instruction": "Do not chase acknowledgement of an unreleased package; first resolve release and the actual permitted scope"
  },
  "commercial_change": {
    "id": "CHG-401",
    "currency": "CAD",
    "proposed_cost_before_tax": 1250,
    "illustrative_estimate_lines": [
      {
        "description": "Illustrative additional preparation allowance",
        "quantity": 5,
        "rate": 150,
        "amount": 750
      },
      {
        "description": "Illustrative materials allowance",
        "quantity": 1,
        "rate": 500,
        "amount": 500
      }
    ],
    "approval": "pending",
    "schedule_impact": "unresolved",
    "next_owner": "Commercial owner",
    "next_action": "Determine actual authority and schedule effect under project arrangements"
  },
  "changed_field_package_release": "held",
  "instruction": "Keep RFI response, drawing review/release, field acknowledgement and cost/schedule decisions separate; this packet does not authorize physical work."
}