OPSMITH WORKED EXAMPLE REPORT — DR-014 v2 Project: RIV-026 / Rivergate Unit 4 retrofit Area: Service corridor C Work date: 2026-10-20 Source: NOTE-014; roster clarification CLAR-014; placeholder evidence PHOTO-01/02 All records and people belong to the worked example. No photographs are supplied in this pack. SOURCE NOTE 6 installers 07:00–15:30; 0.5-hour unpaid break per person. Sheet says 52 hours. 20 access panels delivered; 18 installed. Delivery 90 minutes late; crew moved to other work. Customer requested 2 extra panels. PHOTO-02 arrived the next day. REVIEWED FACTS Labour: 6 × (8.5 − 0.5) = 48 hours. The field lead confirmed a 4-hour entry error in CLAR-014. Installed: 18 panels. Delivered quantity 20 is recorded separately and is not substituted for installed quantity. Delivery: 90 minutes later than expected. No total idle labour claimed; crew continued in another area. Potential change: 2 additional panels requested; refer to CR-007. Daily-report review does not authorize scope or spending. Evidence: PHOTO-02 marked received 2026-10-21 in the scenario; original work date remains 2026-10-20. Weather: not recorded. No weather condition inferred from date or location. DECISION HISTORY v1: review required — labour mismatch and pending PHOTO-02. v2: field lead clarification recorded; late-evidence register updated; Project reviewer B approves the factual example report. No payment, change order or permission to work is approved by this report. NEXT ACTIONS Project manager: review CR-007 v3 before making the applicable change decision. Document reviewer: resolve DOC-02 business-name mismatch separately. SOURCE GUIDE https://opsmith.ca/resources/construction-daily-report-workflow